J
Jeff M.
I have a project that showed overallocations for several
of my resources. I selected all tasks, went to
Project/Task Information/Advanced and selected "As Soon As
Possible" for the Constraint Type. I then leveled
resources and several tasks were affected. In addition,
my Finish date was pushed out by several weeks. However,
when I go back to look at my Resource Graph, although it
looks better I still see overallocations. Is there a way
to level so that all overallocations are removed?
of my resources. I selected all tasks, went to
Project/Task Information/Advanced and selected "As Soon As
Possible" for the Constraint Type. I then leveled
resources and several tasks were affected. In addition,
my Finish date was pushed out by several weeks. However,
when I go back to look at my Resource Graph, although it
looks better I still see overallocations. Is there a way
to level so that all overallocations are removed?