Y
Yoav
Hi,
I asked a similar question a while ago, but I didn't get the answer I looked
for. Now I define the problem better.
I'm basing my leveling mechanism on the resource unit allocation. For each
period where the resource is overallocated I'm searching for the relevant
scheduled tasks, and reducing the units until I get sufficed results.
The problem is that if I report Actual Work that is greater that the planned
Word for any period (using the Resource Usage form), the showed units changes
(e.g. if the units is 100%, reporting for a certain day Actual Word of 16
hours where the Work is 8 hours will change the showed Units to 200%).
Now, I know that the showed units are the maximum among the units per
period, but that fact makes it impossible to perform the Leveling and to
understand the Gantt's allocation. The Team-Member keeps on changing the
units and wastes a lot of time on it.
Do you have any advice to me?
Thanks,
Yoav
I asked a similar question a while ago, but I didn't get the answer I looked
for. Now I define the problem better.
I'm basing my leveling mechanism on the resource unit allocation. For each
period where the resource is overallocated I'm searching for the relevant
scheduled tasks, and reducing the units until I get sufficed results.
The problem is that if I report Actual Work that is greater that the planned
Word for any period (using the Resource Usage form), the showed units changes
(e.g. if the units is 100%, reporting for a certain day Actual Word of 16
hours where the Work is 8 hours will change the showed Units to 200%).
Now, I know that the showed units are the maximum among the units per
period, but that fact makes it impossible to perform the Leveling and to
understand the Gantt's allocation. The Team-Member keeps on changing the
units and wastes a lot of time on it.
Do you have any advice to me?
Thanks,
Yoav