Leveling changes 2hrs to 14,944 hrs

B

Barb K

I have a project that was created in 2007 Project Pro and saved locally. I
imported the project onto the Enterprise server. Now I want to do some
updates. I retrieved the project from the enterprise server and have all of
my work hours. All tasks have the same resource on all of them. There are
many tasks that start on the same day. When I level the resources I have one
task that was 2 hrs of work is now 14,944 hours and one other that was 8 hrs
is now 73,119 hrs. I have not had this problem with projects that were
created and saved directly on the enterprise server.

Has anyone encountered this problem?
 