I have a project with 400-500 tasks, in Project 2007. When I level resources
Project adds work to several of the tasks. Most tasks get delays or splits
but a few it actually changes the work. In some cases it has added several
thousand hours of work. This change is perment (i.e. removing leveling does
not change the work back). This happens in both Standard and Professional.
This makes project almost unusable.
Any ideas?