Leveling Confusion

M

Mitchell

I'm working on project server 03 and set up a series of tasks assigned to one
resource. All the tasks currently start on the same day. The resource is set
to 90%. I'm trying to use leveling to move the tasks out based on the
resource having 90% of his day available for the task. There are no priorites
set on the tasks. Instead of creating a stair case look, as I expected,
leveling has put in delays and moved tasks so they are seperated by a week of
no work or are over allocated in a given day.
 
M

Mike Glen

Hi Mitchell,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 
D

Dale Howard [MVP]

Mitchell --

Since the tasks obviously cannot take place at the same time, why don't you
simply link them together with a Finish-to-Start (FS) depenency? That would
solve the problem nicely and you would not need to mess with the built-in
Leveling tool in the software. Let us know.
 