skipper0802
Hello All,
Possibly someone can advise on this issue.
Environment: Project 2000, XP
I have a workflow.mpp that has multiple projects containing virtually the
same linked, fixed-duration, sequential tasks with priority assigned only to
those tasks (and not to summary tasks). I use resource sharing with a basic
standard calendar, leveling is set to "priority/standard" and tasks are not
to be split or re-assigned. Single entity "work" resources are assigned to
tasks which are to be delayed accordingly if their priority is lower. For the
most part, MSP behaves as expected with the following peculiarity:
Similar tasks with the same resource assigned (different prorities) do not
follow each other sequentially, i.e. task1 (project2) doesn't immediately
follow task1 (project1) timewise; it might schedule earlier or many days
later.
I can't find a reason for this. Can someone shed some light please? I'd
attach files or screenshots but there's no facility to do that in this forum.
Frustrated in Spokane,
Possibly someone can advise on this issue.
Environment: Project 2000, XP
I have a workflow.mpp that has multiple projects containing virtually the
same linked, fixed-duration, sequential tasks with priority assigned only to
those tasks (and not to summary tasks). I use resource sharing with a basic
standard calendar, leveling is set to "priority/standard" and tasks are not
to be split or re-assigned. Single entity "work" resources are assigned to
tasks which are to be delayed accordingly if their priority is lower. For the
most part, MSP behaves as expected with the following peculiarity:
Similar tasks with the same resource assigned (different prorities) do not
follow each other sequentially, i.e. task1 (project2) doesn't immediately
follow task1 (project1) timewise; it might schedule earlier or many days
later.
I can't find a reason for this. Can someone shed some light please? I'd
attach files or screenshots but there's no facility to do that in this forum.
Frustrated in Spokane,