K
Kendra
Hi,
I am having trouble leveling resources, it's pushing the dates out too far.
Here is my scenario below.
Say John has 3 management type tasks:
Task A) 40% Subcontract Oversight task 10/1 - 10/15
Task B) 10% Subcontract Oversight task 10/1 - 10/30
Task C) 10% Subcontract Oversight task 10/1 - 12/30.
I adjust availability in the 'Resource Availability' box to reflect
available unit for John: i.e. 40 % available from10/1 - 10/15; 80% available
from10/16 - 10/30; 90% available from 10/31 - 12/30)
John also has 5 other tasks that falls w/in those time frame (10/1 - 12/30)
& I tried to put appropriate unit allocation - this is a little tricky b/c I
won't have a complete schedule where the start/finish dates will fall w/o
leveling, so I put estimated unit allocation for the remaining 5 tasks.
E.g)
Task 1: 8 hour work, 50% unit allocation
Task 2: 100 hour work, 90% unit allocation
Task 3: 40 hour work, 50 % unit allocation.
etc.
When I level, either it pushes the finish date far out, there is plenty of
free time where John is not working on any tasks - schedule doesn't fill in
those gaps.
It's driving me crazy. Has anyone out there have similar/same type of
problem?
As a temp solution, I may have to break apart some of the large tasks w/
work hours such as 100 & break it up into smaller chunks/tasks to fill in
those free gaps but there are too many of this kinds of tasks but there's got
to be another clever ways that someone else might have thought of.
Any help would be greatly appreciated!!!
Please feel free to contact me at my email: (e-mail address removed) if you have
any leads on this.
Thanks for your time & hope you have a nice day!
Candra
I am having trouble leveling resources, it's pushing the dates out too far.
Here is my scenario below.
Say John has 3 management type tasks:
Task A) 40% Subcontract Oversight task 10/1 - 10/15
Task B) 10% Subcontract Oversight task 10/1 - 10/30
Task C) 10% Subcontract Oversight task 10/1 - 12/30.
I adjust availability in the 'Resource Availability' box to reflect
available unit for John: i.e. 40 % available from10/1 - 10/15; 80% available
from10/16 - 10/30; 90% available from 10/31 - 12/30)
John also has 5 other tasks that falls w/in those time frame (10/1 - 12/30)
& I tried to put appropriate unit allocation - this is a little tricky b/c I
won't have a complete schedule where the start/finish dates will fall w/o
leveling, so I put estimated unit allocation for the remaining 5 tasks.
E.g)
Task 1: 8 hour work, 50% unit allocation
Task 2: 100 hour work, 90% unit allocation
Task 3: 40 hour work, 50 % unit allocation.
etc.
When I level, either it pushes the finish date far out, there is plenty of
free time where John is not working on any tasks - schedule doesn't fill in
those gaps.
It's driving me crazy. Has anyone out there have similar/same type of
problem?
As a temp solution, I may have to break apart some of the large tasks w/
work hours such as 100 & break it up into smaller chunks/tasks to fill in
those free gaps but there are too many of this kinds of tasks but there's got
to be another clever ways that someone else might have thought of.
Any help would be greatly appreciated!!!
Please feel free to contact me at my email: (e-mail address removed) if you have
any leads on this.
Thanks for your time & hope you have a nice day!
Candra