Leveling Error

R

Rob

I am using 2007 desktop.

When I level sometimes, the plan pushes a few tasks out YEARS ahead for what
seems like no reason at all.

Anyone ever seen this?
 
M

Mike Glen

Hi Rob,

Welcome to this Microsoft Project newsgroup :)

Make sure you have no resources assigned to smmaries. Filter for summaries
and check down the Resouerces column.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
J

Jan De Messemaeker

Hi Rob,

Another possible explanation is that you use the resource availability
profile.
Once there is an entry in this list, the periods not covered are 0%
availability.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
R

Rob

Jan,

This is the same project plan as my other post. Maybe they are related
issues?

Thanks again for your help.
 
J

JulieS

Hi Rob & Jan,

I'm guessing a modified Resource max units -- perhaps where the resource is
at zero after a certain time?

Julie
 