To all
Just started using MSP 2003 and have a few problems I am not sure how to
address. I have used other scheduling software but MSP seems to do things a
little differently. I have a project where I want to level my project based
on a material resource rather then time, I have a several tunnels being
advanced similtaniously and want to level based on meters of advance per day.
The meters I can advance per day would be 20 meters and I could work in 8
different headings, each of these can advance 4 meters per day. I want the
project to reflect these advances and show me the best sequence of activites
to give me this advance.
Not sure if my ramblings make sense but basically can I use MSP to give me
the results I am looking for.
AHGA
Shawn
Just started using MSP 2003 and have a few problems I am not sure how to
address. I have used other scheduling software but MSP seems to do things a
little differently. I have a project where I want to level my project based
on a material resource rather then time, I have a several tunnels being
advanced similtaniously and want to level based on meters of advance per day.
The meters I can advance per day would be 20 meters and I could work in 8
different headings, each of these can advance 4 meters per day. I want the
project to reflect these advances and show me the best sequence of activites
to give me this advance.
Not sure if my ramblings make sense but basically can I use MSP to give me
the results I am looking for.