S
Scott Shafer
I am experiencing a very strange problem when I try to level part-time
resources. To see the problem, add two resources and make them available
100%. Then enter two tasks each with a 10 day duration with neither tasking
preceding the other. Then assing the two resources to each task. Leveling
the resources works fine. Next, clear the resource leveling, and make
resource A available 50% and resource B available 30%. When the resource are
noew leveled, one or both of the tasks are shifted to December 2049!. I have
left the leveling order as standard and none of the checkboxes are selected.
Any suggestions?
resources. To see the problem, add two resources and make them available
100%. Then enter two tasks each with a 10 day duration with neither tasking
preceding the other. Then assing the two resources to each task. Leveling
the resources works fine. Next, clear the resource leveling, and make
resource A available 50% and resource B available 30%. When the resource are
noew leveled, one or both of the tasks are shifted to December 2049!. I have
left the leveling order as standard and none of the checkboxes are selected.
Any suggestions?