T
theintern
does leveling always schedule tasks with sooner deadlines first and, if the
deadlines are equal, then schedule the task with the longer duration first?
it appears to be doing this. does anybody know if this is always the case?
if not, i'll have to hard code it to do so using vba.
thanks
scott
deadlines are equal, then schedule the task with the longer duration first?
it appears to be doing this. does anybody know if this is always the case?
if not, i'll have to hard code it to do so using vba.
thanks
scott