S
Sinek
Hi,
We are using project server 2007 and I started having problems with project
lately
I have 2 projects
1. Proj1 - 100 % complete
2 .Proj2 - 100 % complete
I am opening new project (Proj3), creating tasks and assigning resources and
duration, then i level project and get finish date in 01/2008 Project has
about 150 hours of work, and starts today (no links, just simple task list)
When i go to resource usage , i can see tasks in this project and
work/actual work, i can also see other project and commitments section, when
i expand it i see Proj1 and Proj2, in columns actual work/Remaining work i
have same numbets like 140/140, so it looks like that project didn't even
start..
If I open Proj1 (now i have 2 projects open..) everything is ok, in resource
usage section i see remaining work on tasks from Proj1 is zero, and finish
date is 12/2007, when i open Proj2 and do leveling, finsih date makes
sense....
Proj1,Proj2 are published/checked in (few times).
Does any1 know what problem might be?
We are using project server 2007 and I started having problems with project
lately
I have 2 projects
1. Proj1 - 100 % complete
2 .Proj2 - 100 % complete
I am opening new project (Proj3), creating tasks and assigning resources and
duration, then i level project and get finish date in 01/2008 Project has
about 150 hours of work, and starts today (no links, just simple task list)
When i go to resource usage , i can see tasks in this project and
work/actual work, i can also see other project and commitments section, when
i expand it i see Proj1 and Proj2, in columns actual work/Remaining work i
have same numbets like 140/140, so it looks like that project didn't even
start..
If I open Proj1 (now i have 2 projects open..) everything is ok, in resource
usage section i see remaining work on tasks from Proj1 is zero, and finish
date is 12/2007, when i open Proj2 and do leveling, finsih date makes
sense....
Proj1,Proj2 are published/checked in (few times).
Does any1 know what problem might be?