Leveling problems with multiple projects

V

VladimirMasala

Hi,

We are using project server 2007 and I started having problems with
project lately:)

I have 2 projects
1. Proj1 - 100 % complete
2 .Proj2 - 100 % complete

I am opening new project (Proj3), creating tasks and assigning
resources and duration, then i level project and get finish date in
01/2008 :) Project has about 150 hours of work, and starts today (no
links, just simple task list)
When i go to resource usage , i can see tasks in this project and work/
actual work, i can also see other project and commitments section,
when i expand it i see Proj1 and Proj2, in columns actual work/
Remaining work i have same numbets like 140/140, so it looks like that
project didn't even start..
If I open Proj1 (now i have 2 projects open..) everything is ok, in
resource usage section i see remaining work on tasks from Proj1 is
zero, and finish date is 12/2007, when i open Proj2 and do leveling,
finsih date makes sense....


Proj1,Proj2 are published/checked in (few times:)).



Does any1 know what problem might be?
 
M

Mike Glen

Hi Vladimir,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top