Hi,
We are using project server 2007 and I started having problems with
project lately
I have 2 projects
1. Proj1 - 100 % complete
2 .Proj2 - 100 % complete
I am opening new project (Proj3), creating tasks and assigning
resources and duration, then i level project and get finish date in
01/2008 Project has about 150 hours of work, and starts today (no
links, just simple task list)
When i go to resource usage , i can see tasks in this project and work/
actual work, i can also see other project and commitments section,
when i expand it i see Proj1 and Proj2, in columns actual work/
Remaining work i have same numbets like 140/140, so it looks like that
project didn't even start..
If I open Proj1 (now i have 2 projects open..) everything is ok, in
resource usage section i see remaining work on tasks from Proj1 is
zero, and finish date is 12/2007, when i open Proj2 and do leveling,
finsih date makes sense....
Proj1,Proj2 are published/checked in (few times).
Does any1 know what problem might be?
We are using project server 2007 and I started having problems with
project lately
I have 2 projects
1. Proj1 - 100 % complete
2 .Proj2 - 100 % complete
I am opening new project (Proj3), creating tasks and assigning
resources and duration, then i level project and get finish date in
01/2008 Project has about 150 hours of work, and starts today (no
links, just simple task list)
When i go to resource usage , i can see tasks in this project and work/
actual work, i can also see other project and commitments section,
when i expand it i see Proj1 and Proj2, in columns actual work/
Remaining work i have same numbets like 140/140, so it looks like that
project didn't even start..
If I open Proj1 (now i have 2 projects open..) everything is ok, in
resource usage section i see remaining work on tasks from Proj1 is
zero, and finish date is 12/2007, when i open Proj2 and do leveling,
finsih date makes sense....
Proj1,Proj2 are published/checked in (few times).
Does any1 know what problem might be?