D
Dave
Problem 1:
If I set the max units for all of my resources to 100%. Leveling works
correctly. However if I change this to a value such as 50%. Leveling ceases
to function, and I get a lot of 'This overallocation cannot be resolved'.
This can be reproduced fairly easily. Create a project with 2 tasks, with a
work time of 16 hours for each one. Set the resource for both of these tasks
to 'Me'. Level this project Day by Day. MS Project levels this project
correctly. Then change the 'Max Units' for 'Me' to 70%. Try leveling this
again. You then get the 'This overallocation cannot be resolved message'.
I'm not 100% sure this is a bug? Is there some other way I should be
restricting the number of work units my resources can perform? To me,
setting work unit percentage seems the most intuitive way to tell project
that my resource is only available 70% of a typical working week.
Problem 2:
I have a resource set at max 80% units. But starting the next 2 weeks they
are only available 50%. I added the resource to my project and it shows up
as (current) 80%. Next week I guess it would show as 50%. I enter work for
10 hours and the duration changes to 1.56days to match (at 80%). I then set
the "start no earlier then" to next Monday.
What I want is project to spread this 10 hours work sometime in the next 2
weeks. I.e. make it 2.5 days work starting next Monday. But what happens
when project levels resources is the whole two weeks are skipped and the job
starts 2 weeks late. Why? Is there any way to specify the work hours and
have project "mold" these work hours into the resources currently available
time? Even better would be if it could do this taking other tasks into
account. E.g. I have 1 hours free today, 3 hours tomorrow and 2 hours each
the 2 days after that giving me a total 8 hours free. I'd like to enter an 8
hour task and have project schedule my work into these times. Am I asking
too much? To me this is essential for resourcing because that's the way it
works in the real world. I have a set piece of work which must be scheduled
within my resources current availability.
Thanks!
Dave
If I set the max units for all of my resources to 100%. Leveling works
correctly. However if I change this to a value such as 50%. Leveling ceases
to function, and I get a lot of 'This overallocation cannot be resolved'.
This can be reproduced fairly easily. Create a project with 2 tasks, with a
work time of 16 hours for each one. Set the resource for both of these tasks
to 'Me'. Level this project Day by Day. MS Project levels this project
correctly. Then change the 'Max Units' for 'Me' to 70%. Try leveling this
again. You then get the 'This overallocation cannot be resolved message'.
I'm not 100% sure this is a bug? Is there some other way I should be
restricting the number of work units my resources can perform? To me,
setting work unit percentage seems the most intuitive way to tell project
that my resource is only available 70% of a typical working week.
Problem 2:
I have a resource set at max 80% units. But starting the next 2 weeks they
are only available 50%. I added the resource to my project and it shows up
as (current) 80%. Next week I guess it would show as 50%. I enter work for
10 hours and the duration changes to 1.56days to match (at 80%). I then set
the "start no earlier then" to next Monday.
What I want is project to spread this 10 hours work sometime in the next 2
weeks. I.e. make it 2.5 days work starting next Monday. But what happens
when project levels resources is the whole two weeks are skipped and the job
starts 2 weeks late. Why? Is there any way to specify the work hours and
have project "mold" these work hours into the resources currently available
time? Even better would be if it could do this taking other tasks into
account. E.g. I have 1 hours free today, 3 hours tomorrow and 2 hours each
the 2 days after that giving me a total 8 hours free. I'd like to enter an 8
hour task and have project schedule my work into these times. Am I asking
too much? To me this is essential for resourcing because that's the way it
works in the real world. I have a set piece of work which must be scheduled
within my resources current availability.
Thanks!
Dave