C
css34
I have a resource that is scheduled to work 2 fixed duration tasks starting
on 9/29, finishing on 10/16 with a 10% resource allocation on each. So
everyday from 9/29 - 10/16 the resource is allocated to .8h on each task,
which gives her 1.6 hours of work each day. The resource has 20 tasks that
are each 1 hour long that are fixed units, effort driven. I would expect
that when I level, the 1 hour tasks would fill in the remaining available
time in parallel with the fixed duration tasks. What I am seeing is that the
1 hour tasks won't start until after the fixed duration tasks are complete.
What am I missing here?
Thanks
on 9/29, finishing on 10/16 with a 10% resource allocation on each. So
everyday from 9/29 - 10/16 the resource is allocated to .8h on each task,
which gives her 1.6 hours of work each day. The resource has 20 tasks that
are each 1 hour long that are fixed units, effort driven. I would expect
that when I level, the 1 hour tasks would fill in the remaining available
time in parallel with the fixed duration tasks. What I am seeing is that the
1 hour tasks won't start until after the fixed duration tasks are complete.
What am I missing here?
Thanks