JulieS said:
Hi Bryan,
I'm afraid I disagree with the idea of "Don't Level". The difficulty most
folks seem to have with Resource Leveling is they expect leveling to act
as either
1) a resource optimization tool (re-assign resources so they are always
used at their maximum units) or
2) they complain it "messes up their project file" by changing dates.
If you accept what resource leveling can do and what it can't do, I think
it works fine.
I agree with Julie.
Resource Levelling may be all that's needed for simpler projects.
For others it is a great starting point but not the final result (its not
perfect after all).
As a little exercise take the following exercise.
You have 10 people who each need to proof read the same 10 independent
documents. 1 person can proofread a document on 0.5 days and obviously they
can't share the documents when proofreading (only 1 copy of each is
available).
What is the optimal amount of time for completion of proofing?
If you think about it - With everyone starting with a different document and
simply swapping when finished the proofing will be finished in precisely 5
days. Yet the resource levelling result is somewhat different. I believe
this is the difference that Julie's point 1 addresses.