Leveling questions

J

Javier

I have 2 questions:
1- Does the task priority works in a summary task for leveling, or should
you enter the priority for all its subtasks?
2- I have developed a project with resources doing multiple tasks. I have
leveled it and saved the baseline and now I started entering actuals. The
plan changes now when tasks are running behind or ahead of schedule as it
should be. My question is, should I level every time I enter actuals (once
per week) for a better plan, or should I keep it as it is? Any thoughts?
Thanks in advance for your help
 
J

Jan De Messemaeker

Hi,

1. Priority only works on tasks with resources, thus normally NOT on summary
tasks
2. After updating each time use the following process
Clear leveling
Tools, Tracking, update project, reschedule uncompleted work...
Level Now
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 