I have 2 questions:
1- Does the task priority works in a summary task for leveling, or should
you enter the priority for all its subtasks?
2- I have developed a project with resources doing multiple tasks. I have
leveled it and saved the baseline and now I started entering actuals. The
plan changes now when tasks are running behind or ahead of schedule as it
should be. My question is, should I level every time I enter actuals (once
per week) for a better plan, or should I keep it as it is? Any thoughts?
Thanks in advance for your help
1- Does the task priority works in a summary task for leveling, or should
you enter the priority for all its subtasks?
2- I have developed a project with resources doing multiple tasks. I have
leveled it and saved the baseline and now I started entering actuals. The
plan changes now when tasks are running behind or ahead of schedule as it
should be. My question is, should I level every time I enter actuals (once
per week) for a better plan, or should I keep it as it is? Any thoughts?
Thanks in advance for your help