P
Pierre
The conundrum: the automated leveling feature is unreliable, but I can't see
myself manually leveling my big project plan.
The context. I have a big project plan (about 4000 man-days) that gets
tracked with timephased actuals. There are many unrelated simultaneous tasks
- meaning, they can all start at the same time, and they do - and for which
many distinct resources get assigned. As a result, I have a bunch of tasks
that are "in flight", for which assignments all procede at their own little
pace. You basic nightmare as MS Project plans scheduling go.
The tracking process is the following. Every week period:
1. enter the actual worked performed the week before
2. re schedule the remaining work so it starts after the beginning date of
the current week
3. Fix the schedule, so that resources are not overallocated and that
milestone dates can be met.
The problem. I'm trying to use MSP's automatic leveling tool to fix the
schedule. I have always had issues with this tool, but this recent one has
cause me a day's work trying to fix it, and I've not succeeded. Whereas most
published documentation on the subject hammer that the leveling tool only
induces splits and delays (be they on task or assignments), and NEVER changes
the resource assignment work or units, well, it does for me. And it's bugging
me big time, the result being that some assignments get stripped down to a
very low percentage, and the duration augmented to a big value (causing some
tasks to finish in 2049 - thank god there is a limit in the year). But I've
also seen worse results.
Has anyone here experienced this situation? Can you suggest a reason why
project changes the resource assignment units and/or work while leveling? Do
you know of a workaround or a recipe to avoid it happening? Do you have the
address of the authors at QuantumPM that have published "Special Edition
Using Microsoft Office Projecgt 2007", so I can complain about their
assertion that MSProject leveling tool NEVER alters units and work?
In my situation, the only manual alternative I see to this would be to
manually set timephased work, which would be VERY time intensive (and tricky,
as I've experienced situations where MSProject would add work to an
assignment when all you really want, is for it to reschedule the time when
the same amount of work gets planned). Doing so would also actually steer me
away from keeping my schedule as probabilistic as possible. So I'm really
trying to make this automatic leveling feature work for me. And I obviously
need help...
I'm using MSProject 2007 professionnal SP1, unconnected to MSPServer.
myself manually leveling my big project plan.
The context. I have a big project plan (about 4000 man-days) that gets
tracked with timephased actuals. There are many unrelated simultaneous tasks
- meaning, they can all start at the same time, and they do - and for which
many distinct resources get assigned. As a result, I have a bunch of tasks
that are "in flight", for which assignments all procede at their own little
pace. You basic nightmare as MS Project plans scheduling go.
The tracking process is the following. Every week period:
1. enter the actual worked performed the week before
2. re schedule the remaining work so it starts after the beginning date of
the current week
3. Fix the schedule, so that resources are not overallocated and that
milestone dates can be met.
The problem. I'm trying to use MSP's automatic leveling tool to fix the
schedule. I have always had issues with this tool, but this recent one has
cause me a day's work trying to fix it, and I've not succeeded. Whereas most
published documentation on the subject hammer that the leveling tool only
induces splits and delays (be they on task or assignments), and NEVER changes
the resource assignment work or units, well, it does for me. And it's bugging
me big time, the result being that some assignments get stripped down to a
very low percentage, and the duration augmented to a big value (causing some
tasks to finish in 2049 - thank god there is a limit in the year). But I've
also seen worse results.
Has anyone here experienced this situation? Can you suggest a reason why
project changes the resource assignment units and/or work while leveling? Do
you know of a workaround or a recipe to avoid it happening? Do you have the
address of the authors at QuantumPM that have published "Special Edition
Using Microsoft Office Projecgt 2007", so I can complain about their
assertion that MSProject leveling tool NEVER alters units and work?
In my situation, the only manual alternative I see to this would be to
manually set timephased work, which would be VERY time intensive (and tricky,
as I've experienced situations where MSProject would add work to an
assignment when all you really want, is for it to reschedule the time when
the same amount of work gets planned). Doing so would also actually steer me
away from keeping my schedule as probabilistic as possible. So I'm really
trying to make this automatic leveling feature work for me. And I obviously
need help...
I'm using MSProject 2007 professionnal SP1, unconnected to MSPServer.