Hi David,
Yes;I'm sorry to put it bluntly, you do have a misunderstanding of Project's
Leveling.
Leveling will never ever change percent allocation on a task.
All it does is when several tasks together create an overallocation because
they are simultaneous, it will postpone the task(s) with the lowest priority
unttil the overallocation is resolved.
This being said, when it is one task that causes the overallocation (such as
in your case, assignment units are 100% ad max units 75%) postponing isn't
of any help so Leveling will give you a message it is incapable of resolving
the overallocation.
My advice is the following:
Open the Resource Usage view
Insert the column "assignment units"
For the 75% resource, change the first cell to 75%, then select all cells
for that resource in that column, and type Ctrl+D (copy down).
Unless your tasks have fixed duration type, their duration will
automatically be adjusted.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
David said:
I'm new to project, so I apologize if this is silly.... but..... I've
created a project plan, assigned resources, task times, etc... all from the
standard Software Development template. After completing the plan, I found
that one of my resources can only give me 75% of her time. I changed her
Max Units to 75% and tried to level to extent the completion date according
to her availability. It won't level. Am I doing something wrong, I do I
just have a complete mis-understanding of leveling.