D
DenverWaterPM
Hi:
The following scenario is puzzling me: One resource works the following
tasks: One task (A) in one project (project priority 1000, task priority 500)
is scheduled before all other tasks (for example, B with project priority 900
and task priority 950). The time scheduled for A is 0.2h for each of several
days and thus 7.8 h would be remaining available per day for each of these
days. However, project pushes the B tasks to start after A's finish date. I
would have expected that the other tasks are worked such that the 7.8 h are
used. I am allowing splits on tasks, and level the resource working the
tasks using Tools->Level Resources->Level now.
I would be very grateful for any idea.
Christine
The following scenario is puzzling me: One resource works the following
tasks: One task (A) in one project (project priority 1000, task priority 500)
is scheduled before all other tasks (for example, B with project priority 900
and task priority 950). The time scheduled for A is 0.2h for each of several
days and thus 7.8 h would be remaining available per day for each of these
days. However, project pushes the B tasks to start after A's finish date. I
would have expected that the other tasks are worked such that the 7.8 h are
used. I am allowing splits on tasks, and level the resource working the
tasks using Tools->Level Resources->Level now.
I would be very grateful for any idea.
Christine