Hi. If I level a project plan after having moved tasks
around on a plan & cleared leveling, the applicaiton does
not re-level properly. The only way I have been able to
solve this is to re-create the entire plan. Has anyone
ever experienced this?
 
G

Gérard Ducouret

Hello,

When you "move tasks around" you generate date constraints on these tasks.
So the future leveling will be perturbed.