John Sitka
Hi,
I think this is what I want to do. I need to have my resource levelling
responsive to a reschedule of all uncompleted work after "today"
(I don't understand why this is even possible any other way, it implies
booking resources into the past)
So this updating to the "current date and beyond" puts a Start no earlier
constraint on every task. But what would cause a violation of that contraint
when entering actual work.
The routine I discovered this on is
Tools>tracking>Update>reschedule uncompleted to start after <today>
clear levelling across all tasks of a single resource.
level selected resource, allowing splits
All looks good at this stage but when I now enter actual work on a task it
throws a
warning saying this task starts before it's contraint.
Is this one of those nested check boxes on the Options>calculation screen
(status date)
I think this is what I want to do. I need to have my resource levelling
responsive to a reschedule of all uncompleted work after "today"
(I don't understand why this is even possible any other way, it implies
booking resources into the past)
So this updating to the "current date and beyond" puts a Start no earlier
constraint on every task. But what would cause a violation of that contraint
when entering actual work.
The routine I discovered this on is
Tools>tracking>Update>reschedule uncompleted to start after <today>
clear levelling across all tasks of a single resource.
level selected resource, allowing splits
All looks good at this stage but when I now enter actual work on a task it
throws a
warning saying this task starts before it's contraint.
Is this one of those nested check boxes on the Options>calculation screen
(status date)