N
Nina
I have a developer who will be on-call every 3 weeks. While he is on call, he
is at work but can only dedicate 40% of his time to the project.
To capture this in MS Project, I edited resource availability by entering
Available From, Available To and Units information, for example (in AU date
format):
Available From Available To Units
NA 03/07/2008 100%
04/07/2008 10/07/2008 40%
11/07/2008 NA 100%
The problem is, MS Project does not allocate any tasks to the resource while
he is available for 40%. Work required for tasks are entered in days, and the
smallest task requires 1 day worth of work. Levelling is set to automatic,
and "Levelling can adjust individual assignments on a task" and "Leveling can
create splits in remaining work" are selected.
What I want to see is that the resource work on tasks while he is still on
call, so one task spans over multiple days while he is still on call. Any
help would be greatly appreciated as I cannot give deployment dates to the
management until this problem is sorted.
Thanks ..
is at work but can only dedicate 40% of his time to the project.
To capture this in MS Project, I edited resource availability by entering
Available From, Available To and Units information, for example (in AU date
format):
Available From Available To Units
NA 03/07/2008 100%
04/07/2008 10/07/2008 40%
11/07/2008 NA 100%
The problem is, MS Project does not allocate any tasks to the resource while
he is available for 40%. Work required for tasks are entered in days, and the
smallest task requires 1 day worth of work. Levelling is set to automatic,
and "Levelling can adjust individual assignments on a task" and "Leveling can
create splits in remaining work" are selected.
What I want to see is that the resource work on tasks while he is still on
call, so one task spans over multiple days while he is still on call. Any
help would be greatly appreciated as I cannot give deployment dates to the
management until this problem is sorted.
Thanks ..