D
David M C
How can I make Project level a whole summary task rather than its component
parts? At the moment, the individual tasks inside the summary task are
levelled separately and cause what would usually be an 8d summary task to be
spread out over 70 days.
Here's an example of what I have.
70 The Lane
Bathroom Installation
Task1
Task2
Task3
80 The Lane
Bathroom Installation
Task1
Task2
Task3
etc...
Within the Bathroom Installation summary task the resource Bathroom Fitter
is applied to every subtask. When levelling, all the Task1's follow
sequentially, followed by all the Task2's etc. I'd like the whole of the
first Bathroom Installation to be completed before the next begins, without
having the dependencies between tasks. I can get it to work by levelling by
ID only, but stops other tasks in the project from being levelled correctly.
I hope you understand what the problem is, if not I'll try to explain again.
Dave
parts? At the moment, the individual tasks inside the summary task are
levelled separately and cause what would usually be an 8d summary task to be
spread out over 70 days.
Here's an example of what I have.
70 The Lane
Bathroom Installation
Task1
Task2
Task3
80 The Lane
Bathroom Installation
Task1
Task2
Task3
etc...
Within the Bathroom Installation summary task the resource Bathroom Fitter
is applied to every subtask. When levelling, all the Task1's follow
sequentially, followed by all the Task2's etc. I'd like the whole of the
first Bathroom Installation to be completed before the next begins, without
having the dependencies between tasks. I can get it to work by levelling by
ID only, but stops other tasks in the project from being levelled correctly.
I hope you understand what the problem is, if not I'll try to explain again.
Dave