Levelling Task with 2 resources creates split in both resourcess

K

Kirk

Even when I set the check box to allow levelling of individual assigments on
a task, if the task is split due to levelling it interrupts the work for all
resources during the split. This is even if only one resource is
overallocated.

How can I get overallocated resources levelled and keep the resources that
are not overallocated working on the task?
 
J

JulieD

Hi Kirk

have you tried unticking the "levelling can create splits" check box as
well?

Cheers
JulieD
 