D
Dave
I frequently encounter a problem whereby resources are transferred
between projects so resources may be transferred from another project
manager's projects to one of mine (for example).
If I try to update my plan and level it before they have made the change
to theirs then the levelling doesn't give the correct result because the
other plan still shows the resource as having assignments which conflict
with mine.
So, my question is, is it possible to level a plan whilst taking only a
'local' view of some (or all) of the resources?
Saving the plan to a file isn't feasible because of the way we lock
historic actuals which means it is difficult to overwrite existing plans
on the server.
Many thanks.
Dave
between projects so resources may be transferred from another project
manager's projects to one of mine (for example).
If I try to update my plan and level it before they have made the change
to theirs then the levelling doesn't give the correct result because the
other plan still shows the resource as having assignments which conflict
with mine.
So, my question is, is it possible to level a plan whilst taking only a
'local' view of some (or all) of the resources?
Saving the plan to a file isn't feasible because of the way we lock
historic actuals which means it is difficult to overwrite existing plans
on the server.
Many thanks.
Dave