when I set levelling from a date (say, today) I expected all unfinished tasks
to rescheduled in the future. Project seems to leave tasks that were
scheduled before this date but not done where they were timewise. Is it
possible to level in a way to match my expectation.
to rescheduled in the future. Project seems to leave tasks that were
scheduled before this date but not done where they were timewise. Is it
possible to level in a way to match my expectation.