levelling

T

tonyb

when I set levelling from a date (say, today) I expected all unfinished tasks
to rescheduled in the future. Project seems to leave tasks that were
scheduled before this date but not done where they were timewise. Is it
possible to level in a way to match my expectation.
 
J

JulieS

Tony,

Before leveling you need to reschedule any incomplete work -- the
leveling command will not do this. To reschedule from the
Project client: Tools > Tracking > Update Project > Reschedule
uncompleted tasks.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 