Like to reset assignment units like 100%on entire schedule quickly

B

Bud

How can I reset assignment units like 100% on the whole schedule quickly?

I have a schedule where fixed work was used and it has varying assignmnets
units because of that.

I would like to take that schedule, change it to fixed units and than make
all the assignments 100%
 
R

Rod Gill

Hi,

Select all Tasks then click Assign Resources icon (or Alt+F10) then enter
100% for your resources. This will recalculate all durations as with fixed
Units Project will assume Work won't change.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
D

Dave

Bud said:
How can I reset assignment units like 100% on the whole schedule quickly?

I have a schedule where fixed work was used and it has varying assignmnets
units because of that.

I would like to take that schedule, change it to fixed units and than make
all the assignments 100%

Not sure what you mean. You can edit resource assignments in a number
of ways. These include on the Task Form, in the Resource/Task Usage
views or with the resource assignment button.

If you want to change the task type, you can insert the Task Type column
into the Gantt view or you can change it on the Task Form.
 
B

Bud

Hi Rod

I selected teh whole schedule and than clicked (Alt+F10) and I entered 100%.
However, when I did this it didn't really keep that 100% on any of the
resources and than when I was finished it onlt offered me CLOSE. I than
closed but again it didn't change.

What am I doing wrong?
 