M
mdevito
We are using MS Project 2003 (but this happens in 2007 also) and are using
the master/consolidated project function. We have inserted about 13 sub
projects and there are many (thousands) of links between the plans. Because
we're linking between plans, the predecessors & sucessors fields show the
path of the subproject being linked to/from. The plans reside on a shared
drive on a server and so the paths are long. Therefore after 2-3 links on
one task, the field doesn't show all of the predecessors (or sucessors), it
just inserts a "..." for each additional link.
Has anyone ever experienced this before? Is there a way to avoid this?
It's hard to see what's been linked with this abbreviation. I have used the
links to other plans tool, but that can be time consuming to find the
individual task in that screen and doesn't really help because I need the
pred/succ fields to show up on views and reports. I tried mapping a drive to
the folder where the plans are, but Project still shows the entire path.
Any suggestions?
the master/consolidated project function. We have inserted about 13 sub
projects and there are many (thousands) of links between the plans. Because
we're linking between plans, the predecessors & sucessors fields show the
path of the subproject being linked to/from. The plans reside on a shared
drive on a server and so the paths are long. Therefore after 2-3 links on
one task, the field doesn't show all of the predecessors (or sucessors), it
just inserts a "..." for each additional link.
Has anyone ever experienced this before? Is there a way to avoid this?
It's hard to see what's been linked with this abbreviation. I have used the
links to other plans tool, but that can be time consuming to find the
individual task in that screen and doesn't really help because I need the
pred/succ fields to show up on views and reports. I tried mapping a drive to
the folder where the plans are, but Project still shows the entire path.
Any suggestions?