S
ST
Trying to use Outlook to capture time (ie., hours per day) instead of using
My Timesheet and My Tasks in PWA 2007, but we may have a problem and would
like to check with the newsgroup.
Outlook does not seem to allow editing of time periods beyond a couple of
weeks or so from the planned dates of the assignments.
Is this normal? If so, then how would someone be able to enter a few
actuals hours against a task that they've just worked on which was scheduled
to start a few weeks later?
/Spiro Theopoulos.
My Timesheet and My Tasks in PWA 2007, but we may have a problem and would
like to check with the newsgroup.
Outlook does not seem to allow editing of time periods beyond a couple of
weeks or so from the planned dates of the assignments.
Is this normal? If so, then how would someone be able to enter a few
actuals hours against a task that they've just worked on which was scheduled
to start a few weeks later?
/Spiro Theopoulos.