J
jp
Hi,
Is it good/bad practice to link Summary Tasks?
Thanks.
-jp
Is it good/bad practice to link Summary Tasks?
Thanks.
-jp
Jaime,jp said:Ok,
I'm hearing differences of opinion. Which make me think that ultimately
linking tasks to tasks and summary tasks to summary tasks is based on
personal preference. However, I also hear from both of you that new PM using
MS Project
should try to stay clear of using Summary Task linkages.
I think I understand circular references -- when summary tasks are linked to
their own subtasks. Please correct me if I'm wrong on this one or if I'm
omitting
to present other types of circular references not known to me. Point point
comes across kinda clear and kinda confusing. That is when you both say "New
MS Project developers should stay clear of summary task links".
Can you explain the kinds of troubles that can arise from such practices?
If you can describe one or two examples that would be great. At this time,
I'm perplexed as to how these type of linkages would create havoc in
maintaining Project.
Thanks.
-jaime
John;430768 said:Jaime,jp said:Ok,
I'm hearing differences of opinion. Which make me think that ultimately
linking tasks to tasks and summary tasks to summary tasks is based on
personal preference. However, I also hear from both of you that new PM using
MS Project
should try to stay clear of using Summary Task linkages.
I think I understand circular references -- when summary tasks are linked to
their own subtasks. Please correct me if I'm wrong on this one or if I'm
omitting
to present other types of circular references not known to me. Point point
comes across kinda clear and kinda confusing. That is when you both say "New
MS Project developers should stay clear of summary task links".
Can you explain the kinds of troubles that can arise from such practices?
If you can describe one or two examples that would be great. At this time,
I'm perplexed as to how these type of linkages would create havoc in
maintaining Project.
Thanks.
-jaime
Fellow MVPs Dale Howard and Rod Gill are at the guru level (i.e.
that's
well above the expert level). Dale doesn't recommend it and Rod says
he
does link summary lines in some cases. If you feel you are at the guru
level then by all means go for it.
So what's the problem? If project plans were created and then remained
stable (i.e. no editing) then links on summary lines may be ok as long
as subtasks are not linked between summary groups. However, in most
cases project plans are dynamic and the process of maintaining those
plans requires editing that often changes the linking structure.
That's
where the problem comes if summary lines are linked. Unless the plan
is
small the chances of creating links that could become circular
references when other editing is performed (e.g. changes to the
outline
structure).
Project is pretty good at alerting the user if a link edit will
directly
result in a circular relationship. However Project cannot always
detect
conditions that can result in a "backward pass" type of link that may
result when the file structure is modified to reflect the plan's
dynamics (i.e. plan tracking and maintenance).
Master projects with links between tasks in the inserted subprojects
are
even more subject to circular relationships. I have seen more than one
complex master plan structure that contained one or more circular
relationships. The user may not even be aware of it although he/she
may
see some strange file behavior.
The bottom line is that yes, summary line links can be used
successfully. Rod has demonstrated that. But 9 out of 10 experienced
Project users will strongly recommend against it.
John
Project MVPOffice Project Server implementation, training, integration and custom
development' (http://www.msprojectexperts.com)
Jaime,jp said:John,
Thank you and thank you all for your comments and suggestions.
I really appreciate it. I will more than likely fully understand some
of the answers later on as I build more MS-Project plans. At this point
I've understood the lesson -- stay away from linking summary tasks.
Again, thank you all very much for your candid answers.
-jaime
Hi,
Is it good/bad practice to link Summary Tasks?
Thanks.
-jp
LG,Please can someone help me to resolve the issue, Iam too facing the same
issue of circular reference and unable to either outdent or indent
Aviva,GirlGeek said:While trying to convince my clients NOT to put any predecessors or successors
on Summary Tasks, I did a search and found this discussion. Here's what I
usually suggest to people:
If there's a PREDECESSOR on a Summary task, it means that section can't
start until the Predecessor task is done. Figure out which Detail Task within
that section is the real Successor... the one that has to wait until the Pred
is done. Is it the first task in the section? If so, put the Predecessor on
that first task, remove from the Summary task. Is the Predecessor a pred for
ALL tasks in the section? Put on all.
Are the links between the Detail tasks in the section represented fully? If
not, add the right predecessors/successors to them.
If there's a SUCCESSOR on a Summary task, it means that Successor should not
get started until ALL the tasks in that section are done. So add a Milestone
at the end of the section to say that the section is completed (e.g.
"<Summary Task Name> Completed)". Put the Successor on the Milestone line
instead. Make sure all Detail tasks in the section flow through to the
milestone, whether one to the next to next, or each one having the Milestone
task ID in their Successor column.
Apologies to those of you who may think this explanation is obvious.
- Aviva
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.