D
davegb
I've finally figured out what causes the line of dots to the left of a
task bar in the Gantt chart. To recreate this, create a task in the
Gantt, give it a duration of several days, assign a full time resource
to it. Go to the task usage view, and on the first day there was
supposed to be work done, put in 0hrs actual work. Coninue putting in
0 hrs actual work for several days. Then enter some hours of actual
work. Go back to the Gantt. There will be a line of dots (like in a
split task) from the original start date to the start of actual work,
where the blue bar will start.
Now that I've figured out how to create this problem, any ideas on how
to remove the dots and just show the task as the blue bar portrays it,
without the preceding dots.
I've tried changing task type, changing duration, Start, actual start.
So far, no luck. Any ideas from the project gurus will be gratefully
accepted! Guru in this case being anyone who can solve the problem.
David G. Bellamy
Bellamy Consulting
task bar in the Gantt chart. To recreate this, create a task in the
Gantt, give it a duration of several days, assign a full time resource
to it. Go to the task usage view, and on the first day there was
supposed to be work done, put in 0hrs actual work. Coninue putting in
0 hrs actual work for several days. Then enter some hours of actual
work. Go back to the Gantt. There will be a line of dots (like in a
split task) from the original start date to the start of actual work,
where the blue bar will start.
Now that I've figured out how to create this problem, any ideas on how
to remove the dots and just show the task as the blue bar portrays it,
without the preceding dots.
I've tried changing task type, changing duration, Start, actual start.
So far, no luck. Any ideas from the project gurus will be gratefully
accepted! Guru in this case being anyone who can solve the problem.
David G. Bellamy
Bellamy Consulting