R
Riko
Dear all,
from our users of MS Project 2007 Professional I often hear the request,
that it would be useful to link to a deadline instead of the task/
milestone.
The idea behind it is the following: We have a system of inter-linked
project plans. The time when a project A needs to deliver a certain
component for example depends on when project B is ready to install it.
The installation schedule is driven by other things but not by this
component in project A.
Now project leader A would like to link the "ready for installation"
milestone of project B to a *deadline* in his plan associated to a lets
say "compoment ready for hand-over to project B".
This way, his schedule would not be influenced by project B, however he
would clearly see if his planning for this component in project A is
going out of synch.
Do you think, that would be a useful feature? Or is there another way to
implement that?
Thanks and cheers,
Riko
from our users of MS Project 2007 Professional I often hear the request,
that it would be useful to link to a deadline instead of the task/
milestone.
The idea behind it is the following: We have a system of inter-linked
project plans. The time when a project A needs to deliver a certain
component for example depends on when project B is ready to install it.
The installation schedule is driven by other things but not by this
component in project A.
Now project leader A would like to link the "ready for installation"
milestone of project B to a *deadline* in his plan associated to a lets
say "compoment ready for hand-over to project B".
This way, his schedule would not be influenced by project B, however he
would clearly see if his planning for this component in project A is
going out of synch.
Do you think, that would be a useful feature? Or is there another way to
implement that?
Thanks and cheers,
Riko