I want to use excel to input data into project. For example if I enter a
value into cell c3 I want that to relate to a task or subtask in project and
to populate that accordingly. Is this possible? Thanks
 
A

Andrew

Jan

I do this quite a lot. However, I go from project to excel. I have found
that you need to keep both the project and the excel file in the same folder
and if you have a lot of links it can slow things up quite a lot. Could
anyone advise on if VBA could be used for this?

Regards

Andrew
 
M

meg99

Jan

I do this quite a lot. However, I go from project to excel. I have found
that you need to keep both the project and the excel file in the same folder
and if you have a lot of links it can slow things up quite a lot. Could
anyone advise on if VBA could be used for this?

Regards

Andrew

Andrew,
What I have done is put the Unique ID into Excel. Then I create and
import map that updates on the Unique ID

Works quite well.

Glen
 
J

Jan De Messemaeker

Hi,

VBA could be used but

If you want it to be event driven (updating Excel the second you update
Project ) it isn't rocket speed either
Obviously the Excel file has to be open
OTOH VBA has far more possibilities like checking when you do the transfer
and if, depending on values, etc.


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
B

Ben Booth-Jones

Hi Glen

Could you run me through how to do the operation you mentioned below. I
can't seem to get it to work.

Thanks

Ben
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top