link Outlook calender entries to Project

M

Mark Skinner

Is it possible to link the entries in my Outlook 2003 calender to my tasks in
Project 2003 so that a Projects task duration can be more accurately
calculated? This would account for my availability more accurately than just
stating that I am available for a particular percentage of the time. It
would also make it easier to include holidays in a Project.
 
J

JulieS

Hello Mark,

No sorry. You can import tasks from Outlook into Project but cannot
"link" your calendar in Outlook to project.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 