Link the beginning of recurring tasks???

B

bigfish3111

Can you link the group of recurring tasks to another milestone or
activity?

I have monthly milestones that start once each project starts and I
was curious if I could see the instant shift if one of the projects
within the schedule move ahead or behind schedule?

Thanks,
 
J

Jim Aksel

Recurring tasks may be linked just like any other task. Keep in mind that MS
Project will create a "Start No Earlier Than" constraint date on recurring
tasks. So, if you use a recurring task to kick off activity later in the
project it will work fine.

Now suppose other tasks drive the start of your recurring tasks. If your
recurring task moves to the left, you will have to change that by hand. If
they are to be driven to the right, the software should handle that with no
problem.

Linking to a summary task is rarely a good idea, so avoid that.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top