link to task who finish first

J

Jan Peeters

Hi,

Suppose I have three tasks: task1, task2 and task3.
Task3 has to start as soon as possible after task1 OR task2.

If I link task 3 with task 1 AND task 2, then task 3 will only start after
task1 and task 2 finishes. I should however start as soon as possible after
the first task (taks 1 or task 2) finishes.

Thanks.

Hugo
 
M

Mark Durrenberger

I'm afraid that the dependencies are "AND" functions not "OR" functions.

And despite my wracking my brain, I can't seem to come up with an elegant or
inelegant work-around...

Mark


--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top