N
nippy.sweetie
I have a project structure inherited from one of the major consulting
firms (so I am assuming that they have researched that this approach
is the optimal one for managing large projects ;-) )
I have one main file 'Project a.mpp' (but not a master file) which
illustrates the summarised information on the project. There are then
a further 12 project files 'Project b.mpp' - 'Project m.mpp' which can
be managed independently - with the key summary tasks 'linked' into
the main project file 'Project a.mpp'.
within 'Project a.mpp' I can display the 'linked fields' column -
which is marked 'yes' for linked fields. When I click on the linked
task - MS Project opens the corresponding mpp file.
So far so good.
The issue I have is that in the 'Project b.mpp' file - the task shows
a duration=38 days and work=327days - but in the 'Project a.mpp' the
task is showing duration=38 days and work=38days. This means that my
workload for the entire project is underestimated. I notice that the
'type' column is also not the same between the 2 files. 'Project
b.mpp' shows 'fixed duration' yet the display of the linked field in
'Project a.mpp' showed some other type - but can be edited (yet I
thought data could not be changed for a linked field without removing
the link).
In addition, I presume if I wanted to run reports per resource effort
or resource cost from within 'Project a.mpp' - I would not see the
true totals across 13 linked files.
Should I therefore abandon this project construction before I go in
too much deeper and reformat everything to 'master' and 'dynamic
subprojects'?
some 'Best practice' and 'common pitfalls of using linked files' would
be appreciated.
Many thanks for any advice
firms (so I am assuming that they have researched that this approach
is the optimal one for managing large projects ;-) )
I have one main file 'Project a.mpp' (but not a master file) which
illustrates the summarised information on the project. There are then
a further 12 project files 'Project b.mpp' - 'Project m.mpp' which can
be managed independently - with the key summary tasks 'linked' into
the main project file 'Project a.mpp'.
within 'Project a.mpp' I can display the 'linked fields' column -
which is marked 'yes' for linked fields. When I click on the linked
task - MS Project opens the corresponding mpp file.
So far so good.
The issue I have is that in the 'Project b.mpp' file - the task shows
a duration=38 days and work=327days - but in the 'Project a.mpp' the
task is showing duration=38 days and work=38days. This means that my
workload for the entire project is underestimated. I notice that the
'type' column is also not the same between the 2 files. 'Project
b.mpp' shows 'fixed duration' yet the display of the linked field in
'Project a.mpp' showed some other type - but can be edited (yet I
thought data could not be changed for a linked field without removing
the link).
In addition, I presume if I wanted to run reports per resource effort
or resource cost from within 'Project a.mpp' - I would not see the
true totals across 13 linked files.
Should I therefore abandon this project construction before I go in
too much deeper and reformat everything to 'master' and 'dynamic
subprojects'?
some 'Best practice' and 'common pitfalls of using linked files' would
be appreciated.
Many thanks for any advice