Linked Project Baseline?

J

John Castle

If I have a project which has been baselined and then
linked into a higherlevel project which has also been
baselined - which baselined dates are displayed in the
higher level project? - the lower level baseline project
dates or the higher level baseline project dates?
 
S

Sean

John:

If you've inserted a baselined project into another
baselined project, the baseline fields will correspond to
their respective baselines.

This refers to 2003 functionality.

Hope this helps!
 