Linked project tasks show in PWA projects

N

New2Project

On MS Project I have a Master Project. I have linked projects together so
that when I manually move one task to start later in a project, it will move
the other tasks to start later aswell in the other linked projects. This
makes sense and works well as I will not have to manually move every single
task in other projects to start later.

One problem. In PWA > Project Center and a linked project is clicked, It
will show tasks for that project AND also tasks that are linked from other
projects. Ideally, people can access the PWA and see the tasks for that
Project only. It can be confusing and misleading with other tasks in there
from other projects.

Any advice on how to get rid of these tasks? If I don't link projects
together, what else can I do? Any other way around this problem?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top