Hi,
I have a number of project plans all linked to a master plan so that I can
use it to gain a high level view and oversee projects. However, when I open
up the master plan on its own, all start times for the projects default to a
set date so the overall Gannt looks like a number of projects are all
starting at once. Only when I open up the corresponding lower level plan do
the start dates correct themselves.
Is there any way round this as I want to be able to view an accurate
overview without having to open all documents.
Any help gratefully appreciated,
cheers
I have a number of project plans all linked to a master plan so that I can
use it to gain a high level view and oversee projects. However, when I open
up the master plan on its own, all start times for the projects default to a
set date so the overall Gannt looks like a number of projects are all
starting at once. Only when I open up the corresponding lower level plan do
the start dates correct themselves.
Is there any way round this as I want to be able to view an accurate
overview without having to open all documents.
Any help gratefully appreciated,
cheers