Linked Projects

S

Sally

We have a number of sub plans that are linked to a master plan. When one
user (who is set up like all of the rest) opens her plan, she receives "file
not found" under "differences" in the Links between Projects dialog box. I
can find no reason for this in her permissions.

Thanks!!!!!!!!!
 
G

Gary L. Chefetz [MVP]

Sally:

In order for PMs to work with linked plans with full functionality, they
must have at least read-only access to all the plans linked to the one
they're opening. Does that help?
 
S

Sally

Hi Gary,

yes it does help because they are set up to have access to their own sub
plan but not the others.

Thanks!!!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top