T
Tricia R.
We have implemented Project Server and had a consultant help us with the
initial configuration and recommended we do not allow Master Projects (I
can't remember exactly why at this point).
In addition to our PMO projects, we would like to start tracking the small
projects (under 80 hours) but one of our managers would like to link these so
that he can assign 3 or 4 of these to one resource and link them such that
the dates from one drive the dates in the others. Is it possible to set a
predecessor in a project as task from another project? Thanks!
initial configuration and recommended we do not allow Master Projects (I
can't remember exactly why at this point).
In addition to our PMO projects, we would like to start tracking the small
projects (under 80 hours) but one of our managers would like to link these so
that he can assign 3 or 4 of these to one resource and link them such that
the dates from one drive the dates in the others. Is it possible to set a
predecessor in a project as task from another project? Thanks!