Linking a Task with Project Start AND End

Z

ZakTaemur

Is there a way in MS Project to make a task (at ANY indentation level)
to have a Start AND End dates based on the overall project Start and
End dates ?

Each task in MSP has a Start and End dates but I cannot see any way as
to how I can achieve the above.

Any help would be appreciated ..
 
D

Dale Howard [MVP]

TaemurZ --

You are more than welcome, my friend! :)




Zak --

You might consider using a hammock task for this purpose. However, keep in
mind that doing what you are requesting forces the task onto the Critical
Path. Here's how to do it:

http://project.mvps.org/faqs.htm#Hammock Tasks

Hope this helps.










- Show quoted text -

Works a treat ! Did not know they are called Hammock tasks :)

Many thanks Dale ..
 