Linking Convention

N

NevilleT

I am curious if there is some convention about linking. I typically have a
milestone at the end of a summary task (the deliverable from the summary
group) and link that to the next summary task if they are happening
sequentially.

For example suppose we have two summary tasks "Build Deliverable One" and
"Build Deliverable Two" and the last task (milestone) in the first summary
task is "Deliverable One Available". I would link the Milestone "Deliverable
One Available" to the summary Task "Build Deliverable Two".

What is the view of other PMs?
 
J

Jan De Messemaeker

Hi Neville,

Interesting! Not so long ago there has been a discussion among the MVPs
about this subject. You may read some of the consensus on FAQ 48: Summary
task linking.
URL of the faqs in my signature.
 