Gidday All,

Does anyone know how to get MS Project to automatically send an E-mail to a
nominated party via MS Outlook, pending expiration of a milestone in MS
Project? This seems such a logical thing to do, i.e. an automatic reminder to
complete an assigned task.
 
L

ldh0901

You could also go into PWA and set up alerts in there. I can't remember the
specific steps on 2003 but on 2007 just go to server settings and then Alerts
and Reminders.
 
P

Paul Conroy

One of the challenges here is that you will need to open the plan to invoke
the sending of email.

Why not create a view which filters all outstanding tasks/assignments ?

As Rod says, the email function is available with Server.
 