S
Steve Scott
e.g. I have 5 tasks of equal duration all starting and finishing on the same
dates. I want to be able to drag ANY of the 5 tasks to start earlier or
later and then see the others dragged as well so that they all line up as
equal duration and all starting and finishing on the new dates.
Simple SS and FF links don't work and produce different results depending
upon which task in the sequence is moved first.
Any ideas on how to tackle this?
Thanks
dates. I want to be able to drag ANY of the 5 tasks to start earlier or
later and then see the others dragged as well so that they all line up as
equal duration and all starting and finishing on the new dates.
Simple SS and FF links don't work and produce different results depending
upon which task in the sequence is moved first.
Any ideas on how to tackle this?
Thanks