S
Saadia
Hi,
Just started using MS project 2007(Standard).
I have several jobs on the go, and have each job name listed as a task.
All my tasks are linked together and i have fixed duration picked. I am
assigning
several employees to each job. Some employess will be working on two or more
jobs on the same day. So let's say Jay is at Job 1 on the 20th for 4 hrs and
at Job 2 for 4 hrs the same day. When i set this up in the resource usage
sheet it automatically assigns every employee that was scheduled to work on
job 2, for 8 hours even though i had not assigned any time for them. Is also
gives me a message that the second job is being started before it's scheduled
start date which is understandable. Is there any reason it would do this..or
is there something i'm doing wrong? Any help would be appreciated. Thanks
Just started using MS project 2007(Standard).
I have several jobs on the go, and have each job name listed as a task.
All my tasks are linked together and i have fixed duration picked. I am
assigning
several employees to each job. Some employess will be working on two or more
jobs on the same day. So let's say Jay is at Job 1 on the 20th for 4 hrs and
at Job 2 for 4 hrs the same day. When i set this up in the resource usage
sheet it automatically assigns every employee that was scheduled to work on
job 2, for 8 hours even though i had not assigned any time for them. Is also
gives me a message that the second job is being started before it's scheduled
start date which is understandable. Is there any reason it would do this..or
is there something i'm doing wrong? Any help would be appreciated. Thanks