I have created a master schedule to view all milestones from all my schedules
in one place. It works fine except for one column. When I open the Baseline
finish in the master schedule to compare the dates, it shows only N/A. Is
there a way to bring the baseline finish information from the linked
schedules into the master schedule so I can view the variance? I am using
Project Server 2003. Thanks for your help.
Johnnie