Johnnie

I have created a master schedule to view all milestones from all my schedules
in one place. It works fine except for one column. When I open the Baseline
finish in the master schedule to compare the dates, it shows only N/A. Is
there a way to bring the baseline finish information from the linked
schedules into the master schedule so I can view the variance? I am using
Project Server 2003. Thanks for your help.
Johnnie
 
D

Dale Howard [MVP]

Johnnie --

Unfortunately, it appears a limitation of using a master project is that the
subprojects show Baseline information for only the tasks and summary tasks,
but not for the Project Summary Task. I know of no way to work around this
problem. Sorry.
 
J

Johnnie

Dale,

Thanks for help. The work-around I am using is to manually enter and save
the base line dates from the supporting schedules. Info for future use if
this situation ever arises again.

Once again. Thanks.

Johnnie
 
D

Dale Howard [MVP]

Johnnie --

You are more than welcome for the help, my friend! Your workaround sounds
fine, but a bit labor intensive. :)
 