I have a small parking lot project which will be completed in phases. We are
adding parking in several locations, which requires us to do the same three
tasks several times. I want to have three task names, split into 4 sections
each. I would like the first split section of the first task to link to the
first split section of the second task, the first split section of the second
task to link to the first split section of the third task. Then the first
split section of the third task to link to the second split section of the
first task. Is there a way that "Project" can do this?
adding parking in several locations, which requires us to do the same three
tasks several times. I want to have three task names, split into 4 sections
each. I would like the first split section of the first task to link to the
first split section of the second task, the first split section of the second
task to link to the first split section of the third task. Then the first
split section of the third task to link to the second split section of the
first task. Is there a way that "Project" can do this?